COMMUTED SUMS
(i) To receive an update on outstanding developer discussions/negotiations:
(a) Copthorne Barracks Play and Open Space – offsite contributions to play and open space – awaiting progress with Pavilion
Extension & confirmation of drawdown of Commuted Sums from the planning authority
(b) Barratt Homes/Bovis Homes – Mytton Oak Road – scheduled adoption Autumn 2020 – costing for snagging list agreed by
developers, awaiting sign-off
(c) Shrewsbury South Urban
(i) Sutton Grange site – ongoing – likely transfer in 2021
(ii) Bellway Homes site – discussion on land adoption and adoption of acoustic fencing
(iii) Galliers site – early discussions on land adoption
(iv) Community Centre – location on the site
(d) Ingleby Way – Adoption & Maintenance of open space – now ready following clarification of hedgerow ownership – awaiting
confirmation of title from developer
(e) Holgate Drive – Adoption & Maintenance of open space - awaiting completion of snagging– paperwork signed;
(f) Belvidere Paddocks/Hillside Drive – Adoption & Maintenance of open space – ready awaiting transfer– paperwork signed;
(g) Arlington Way – Adoption & Maintenance of open space – Land transferred – awaiting £60k transfer S106 money from Shropshire
Council;
(h) Sweetlake – Development of play area and future adoption of open space – Play Area currently in construction. Developer working
through snagging list. Legal teams in discussions
(i) Crowmoor House – s106 agreement for offsite play & open space contribution to be used for Upton Lane & Monkmoor Recreation
Ground – two-staged payments on trigger on percentage occupied properties. Council may need to bankroll work at Upton Lane Rec
|